One of 8 volumes of the environmental assessment. for the Lower Mainland 500 KV line. Hard copy at Public library.
File Photo :KDG
The completed work saw a 3rd lower mainland 500 KV line go through Merritt on its way to the Lower Mainland from Revelstoke. The project had rigorous permitting process and is complete since last year including a new substation here in Merritt .
The local 200 million dollar Green energy project is delayed opening until next fall a full year past the expected time. Something a private operation trys to avoid.
At this writing a small piece of the 138 KV line at central park is going underground. the poles it will be replacing were placed next to a housing walled community and a golf course.
On this Day: January 26th 1992
Russia announces that they are no longer targeting the west with missiles.