The Trans Mountain expansion issued this list in September 2017 the start date of its project. The Ledcor  partnership contractor  effects  the Merritt area most as well as Surerus Murphy in the Coquihalla. At this writing the contractors most used motel is not hosting any crews.

 

Spreads 1 & 2: Edmonton/Yellowhead

  • Contractor: Midwest Pipelines Inc.

Spreads 3 & 4: North Thompson

  • Contractor: Ledcor Sicim Limited Partnership

Spread 5A: BC Interior

  • Contractor: Surerus Murphy Joint Venture 

Spread 5B: Coquihalla – Hope

  • Contractor: Macro Spiecapag Joint Venture

Spread 6: Fraser Valley

  • Contractor: Somerville-Aecon Energy Group

Lower Mainland:

  • Contractor: Kiewit Ledcor TMEP Partnership
  • Lower Mainland scope includes Spread 7, Burnaby Mountain tunnel and three terminals: Westridge Marine Terminal, Burnaby Terminal and Sumas Terminal

The Trans Mountain expansion is  a 7.4 billion dollar twinning of a n existing pipeline from Edmonton to Burnaby. There is currently a court order for a concern over routing through the Coldwater Band in Merritt. The concerns are over ground water and proximity to the Coldwater river.