The Transmountain expansion project has some new financial and operative numbers that they posted as of February 18th 2022.The cost of the expansion is now going to be 21 billion dollars. The completion date is for the third quarter of 2023. The old completion date before covid and the floods and the wildfires was to be December 2022.
Financing costs are up, this may be due to the fact that they have to borrow more money and not get funded by the government as the finance Minister has cut the tap off. We can expect a little leaner mindset going forward to completion.